Construction Plan
26 Done
Construction
3 Q 2020
Phase 1
3 Q 2023
Phase 1
3 Q 2023
Phase 2
4 Q 2024
Phase 2
4 Q 2024
Phase 3
3 Q 2025
Project progress
Construction plan
Phase
20202 Q3 Q4 Q
20211 Q2 Q3 Q4 Q
20221 Q2 Q3 Q4 Q
20231 Q2 Q3 Q4 Q
20241 Q2 Q3 Q4 Q
20251 Q2 Q3 Q4 Q
20261 Q2 Q
THE PAVILLIONS EL NIDO
2 Q 2020 - 3 Q 2025
MILESTONE DATES
2 Q 2020 - 3 Q 2025
Design Stage
2 Q 2020 - 2 Q 2022
Procurement Stage
4 Q 2020 - 2 Q 2023
Construction Stage
1 Q 2021 - 2 Q 2025
New Consultant Appointment
1 Q 0 - 2 Q 0
MEPF Consultant
1 Q 2021 - 1 Q 21
QS Consultant
1 Q 2021 - 1 Q 21
QS Services
4 Q 2021 - 3 Q 2022
QS Phase 1
4 Q 2021 - 2 Q 22
QS Phase 2
1 Q 2022 - 1 Q 22
QS Phase 3
4 Q 2021 - 2 Q 2022
Design Stage
2 Q 2020 - 4 Q 2022
Design Phase 1
2 Q 2020 - 2 Q 2022
Design Phase 2
2 Q 2020 - 4 Q 2022
Design Phase 3
3 Q 2021 - 3 Q 2022
Procurement Stage
3 Q 2021 - 3 Q 2023
Procurement Phase 1
3 Q 2021 - 4 Q 2022
Procurement Phase 2
1 Q 2022 - 3 Q 2023
Procurement Phase 3
4 Q 2021 - 3 Q 2023
Construction Stage
3 Q 2020 - 3 Q 2025
Construction Preliminaries Work
3 Q 2020 - 1 Q 2021
Construction of Phase 1
4 Q 2020 - 3 Q 2023
Mobilization & Site Preparations
4 Q 2020 - 3 Q 2021
Construction of Land Villas
4 Q 2020 - 2 Q 2023
Construction of Overwater Villas
4 Q 2021 - 3 Q 2023
Construction of Facilities
4 Q 2021 - 3 Q 2023
Land Development Works
1 Q 2021 - 2 Q 2022
Construction of Access Roadworks
1 Q 2021 - 3 Q 2021
Construction of Main Roadworks
4 Q 2021 - 4 Q 2022
Construction of Phase 2
3 Q 2023 - 4 Q 2024
Remaining Land Villas
3 Q 2023 - 3 Q 2024
Remaining Facilities
3 Q 2023 - 4 Q 2024
Completion of Land Development Works
3 Q 2023 - 3 Q 2024
Construction of Phase 3
4 Q 2024 - 3 Q 2025
Construction Stage Completion
3 Q 2025 - 3 Q 25
As the coronavirus-2019 (covid-19) spreads throughout the Philippines, several issuances by different local government units and agencies have caused the delay in the progress of the construction. The covid-19 pandemic is an event beyond the control of El Nido Beach Resort Inc. (“EBRI”), its affiliates, partners, and suppliers, and the government issuances affecting movement as well as transportation of necessary materials have affected the construction timeline. EBRI is exerting its best in order to finish the project within the schedule but does not guarantee the same due to the uncertainty of the covid-19 pandemic and governmental orders which it has to comply with.