ProgressOur Commitment to Deliver

Stay informed with construction progress, projects insights, technical reports and experience how we make things happen at El Nido Beach…

The progressConstruction Updates

Keep yourself informed on the most recent developments surrounding El Nido Beach’s premium hospitality projects’ construction progress, insights, and reports. Be fully engaged in the experience of observing how we transform our blueprints into concrete reality. Our passion and proficiency will enable you to witness, firsthand, our ability to make things happen at El Nido Beach.

  • August
  • July
  • June
  • May
  • April
  • March
  • February
  • January
  • December
  • November
  • October
  • August
  • July
  • June
  • May
  • April
  • March
  • February
  • January
  • December
  • November
  • October
  • September
  • August
  • July

August 2023

In August 2023, the project saw remarkable strides in its journey towards completion. Building activities were vigorous, reaching key milestones that include the full completion of structural framing for Villa22 and MUV11. The concrete pouring for MUV15’s foundation not only marks a new phase for this unit but also signifies our dedication to robust and durable construction. Additionally, the roofing and exterior walls for multiple units are nearly complete, providing a glimpse into the final appearance of our project. As we moved forward with electrical and plumbing works, safety and quality checks were rigorously conducted, reflecting our unyielding commitment to excellence. With the project now rushing towards completion, the team remains steadfast in its dedication to timely and high-quality execution, setting the stage for the advanced interior works that lie ahead.

Construction Progress Update for August 2023

We are pleased to update you on the construction progress for the month of August 2023. Below is a summary of key tasks that were executed, organized by the area of work.

Construction:

  • Villa 21: Completed C purlins to the connection of I-beam.
  • Villa 22: Installation of insulation, and completed plastering works.
  • Villa 11: Multiple manhole installations and pourings were completed. Excavation for catch basin 11-A also underway.
  • MUV 14: Chipping and plastering works completed, along with U-Channel installations.
  • MUV 12: Drop ceiling at the bathroom and cornice painting were completed.
  • MUV 15: Finishing works underway.
  • MUV 13: Ceiling installation in progress.

FOH-BOH Areas:

  • Installation of Column Ties for concreted tie beam.
  • Soil compaction and leveling works for SOG (Slab on Grade) are complete.
  • Ongoing pouring of suspended slabs.
  • Elevator pit has been concreted.

Roads and Parking:

  • Road 11: Clearing for parking areas and surveying completed.
  • Road 4: Dexpan application along villa 13 completed, and stone breaking is ongoing.
  • Road 1: Installation and backfill of retaining wall.

Canal and Drainage:

  • Fabrication of forms and rebars for cover canal ongoing.
  • Several stages of canal pouring complete.
  • Excavation and pouring for catch basins are underway.

Other Works:

  • Manholes: Construction by contractor Darwin Abaca completed.
  • Retaining Walls: Construction by contractor Jose Caguioa is underway.
  • Mechanical Works: Stockpiling completed.
  • Seminar: Zoomlion testing and Seminar for Pumpcrete usage conducted.

Health and Safety:

  • Extension cables crossing the road have been covered with plywood to prevent cable damage following HSE compliance site inspections.

We are committed to keeping you informed and are on track for project completion as planned. Thank you for your continued trust and investment in this project.

Progress Report

The monthly progress report for the month of August 2023 is now available for downloading. Should you have any inquiries or clarifications, please do not hesitate to send them to us by emailing at support@elnidobeach.com

DOWNLOAD REPORT

The El Nido Beach Investment Report 2023

Learn more about market forecasts & exciting opportunities to enjoy invaluable financial benefits with special privileges in Southeast Asia's fastest growing tourism industry.